2.Comparing Project A and B based on NPV and IRR,ifMARR=10%.01234Project-70001000200060004000AProject-40001000100030003000B问题:(1)Calculate the NPV and IRR of each project(15分)(2)How to choose the best Project’?Why?(10分)